If your the only member of the team is it really worth going through the same agile development process that you would in a team of eight?

Isn’t it quicker to just crack open Visual Studio and start coding?   After all your the customer so you know what you want right?   You not going to have to deal with any of the social complexities that conspire against you. You’re going have the hottest of communication with the dev team,  the dev and test roles will have an interment knowledge and the scrum master won’t really have to do anything as there is not going to be any blockers on this project.

Right?

So I started down this path and before I knew it I had some weird project created with bits of code and SharePoint artefacts but not really seeming to make any progress.   I was easily distracted by other things and didn’t really have a feel for how long it would take and when I could say I was done.

STOP!

What was I doing!  I spend my time trying to help people develop better, to take small steps and sometimes big steps to help produce better software..   why was I not practicing what I preached?

I stopped!

Deep breath, deleted all the rubbish I can previously created and got back to basics.

The Team

I have a team,  the fact that some (in this case all) of the roles were done by the same person was ok; that happens often in agile teams.

Design

Yes, you heard me right here.  Eric Shupps would be proud of me :) .   I’m not going to jump into Visual Studio and crank out code starting [TestFixture] I need to do some design work first, even though this application is going to be small I still need to put in the time on the upfront design.  I need to think through the solution at a high level.

Here I used the opportunity to try out the great Balsamiq application,  which I stumped up the $79 license fee for and download the desktop version.

Blurred out Balsamiq Design

I’ve deliberately blurred the image but you get the idea of what the mock ups look like, and these take only a matter of minutes to produce.  Definately something you should consider if your currently trying to do this in Visio or heaven forbid cranking out HTML mockups.

The few UI based mockups actually helped me to understand how the application would work for the end user, which in turn provided a clear vision for the way the solution would be developed.

User Stories

I didn’t need to do any remote collaboration on the User Stories so I was able to get back to basics and use one of the white boards in my office as the task board.   I wrote the user stories out on post-it notes and added them to the board along with rough estimates for each one.

image

Here you can see I’m using a very common step of status on my task board

Backlog - This is where I add all stories that came out of the design,  they are all user focused with nothing specific about the implementation.  No stories like ‘Use jQuery to make it nice’  these are user stories.  If I think of something while i’m coding or testing, or even having a beer I can just write it to a post-it and stick it on the backlog.

Sprint – I like Scrum so adopt a Scrum Esq. style to my process.  The sprint will be where I put the stories I plan to do next.  The amount is based on the estimate and also the sprint length.   In this project I’m doing stupily short sprints of 2 days each.

In Progress – When I pick off a story to work on it goes in here,  if you’ve ever looked at the Kanban approaches your looking to keep this ‘In Progress’ to a defined level.  I like to try and move things through to ‘Done’ before picking off new stories.

Verify – When I think it’s been coded properly and dev tested I move the story here.   Verify is where I would validate the code on another environment – i.e. a non-dev box,  one with multiple web front ends.  At this point I also look at introducing some form of automation for both the build/deployment and also the acceptance testing.

Done – This is when it is really really done,  there is nothing left to do, no documentation, no tests or tweaks,  the code is production ready.

Sprint 1 – Day 1

Having selected the user stories for the sprint it was time to setup my dev project and get some of the foundations in place.   If you follow me on twitter you will know that I previously spent time producing a decent SharePoint development Virtual Machine so it was very quick for me to roll out the few things I needed to get going.   A SharePoint team site in which I could spike and test my code,  a VS2008 solution and class library project in which to start cranking out some code.

At the end of Day 1 my board looked like this:

image

One of the stories I felt was ready for verification and another I was making good progress on.   At this point I had nothing ‘Done’ my burndown in the morning would look a bit sad,  but that’s OK that is often the case at the start of a project or sprint.  I also don’t at this point have a verification setup so this is going to slow me down a bit on Day 2.

Day 1 has been good,  I have the basic project structure defined.   I was able to build a WSP with the SharePoint features I needed to complete the first story and was able to deploy and test this on my dev machine.

People that have read my blog or seen me talk at conferences and user groups know that I am very keen on doing things right; I like to see Unit Tests and better still I want to see people at least trying Test Driven Development.   However at the end of Day 1 I was yet to write a single line of C# code, neither in test form or production code.   So did I really do development on day one?

Well I think I did, only the language used was XML and a little bit of CAML and for these items I do not know of any way, that makes sense, to unit test.  I often think that the XML we define as part of SharePoint projects are more inline with doing configuration,  we are just setting up SharePoint using a specific configuration and the testing for this should naturally falls into the integration space and will be picked up during verification.   That is not to say as a developer I do not validate it,  I need to ensure that it works as expected in my environment before I can move it over to the Verify column and it’ is the job of the tester to make sure this happens.  For this project the tester (me) was adamant that it all worked as they didn’t want to have to waste time on silly errors.

Interesting Test

One thing that I will be having to do with this project is fit it around real work, the sort that helps to keep food on the table sort of work.   This means that the sprints although 2 days in length the elapsed time may be significantly longer.  I know that this will impact on the velocity as I will lose some of the momentum during these breaks, however the benefit I have from adopting a more defined process is that it will be significantly easier for me to pick up the project.   Imaging if I had to go back to the mess of code I had originally created after a weeks break!

I’m really interested to see if my agile development with a team of one really does make a significant impact on the way I develop the code, on the time it takes to complete it and on the quality of the solution created at the end.

Find out what happens on Day 2.

Monday, May 4th, 2009



Being an advocate of SharePoint as an application platform I looked long and hard for a decent implementation of a Scrum and have always been found wanting.  I have seen simple examples where any power user could set things up but found the lack of any Burndown charts meant you lost probably the most important part of Scrum – the visibility.

I have found that VersionOne is one of the best products on the market, although it has a lot of options which tends to put off new teams.

For those that use Team Foundation Server your probably going to head towards the Scrum for Team System developed by Conchango.  I’ve not used this in anger so am unable to comment on how well it works however this solution is not really a SharePoint specific solution as it requires you to make the commitment to using Team Foundation Server.

Bil Simser did a good post on scrum tools,  although its nearly 3 years old still has some good links.   Again however the tools are not specifically SharePoint.

Why the SharePoint Obsession?

SharePoint is the collaboration tool of choice, companies have deployed it and it is being used with varying degrees of success.  People have become familiar with the how to add items to a list, how to upload documents into a document library and for the more advanced how to build engaging dashboards.

What is the biggest thing you get from adopting scrum?  ‘Visibility’

What do you need to encourage to make Scrum work?  ‘Collaboration’

SharePoint is the natural platform choice on which to build a Scrum tool.

Introducing Project Aberdovey

As with all good development teams I think it is right that your development project should have a name,  and in keeping with some big companies in the Seattle area 21apps uses place names.   Aberdovey, or as it’s spelt in Welsh Aberdyfi, has probably one of the best beaches in the UK and is located 50 miles west of the office.

Put simply, Project Aberdovey is a Scrum tool for SharePoint.

There are a few aims for the project:

  1. Produce a fantastic Scrum tool built on SharePoint
  2. Develop the solution using agile techniques including TDD
  3. Dogfood the solution as soon as possible – what better way to develop the right solution
  4. Open development – I want to give feedback on the challenges but also welcome your input

I will be looking for ways to give people visibility,  I am looking at codeplex as an option but welcome any suggestions.

Sunday, February 8th, 2009



As promised the slide deck from my Agile SharePoint Development with Scrum.

Abstract

Provide an introduction to Agile development using Scrum and discuss how the iterative approach to development helps the customer to get the solution they want. Look at how this approach works when applied to SharePoint projects, how it helps leverage more of the core platform and focuses effort on the biggest value areas. We will look at the challenges this brings to your development team by doing early integration, dealing with upgrades and changes and understand how addressing the hard things early is the right approach. We will also discuss how Scrum gives visibility of the project and brings both good and bad news. How getting customer engagement is the primary challenge and how the flexible approach is often at odds with the way work is contracted.

Agile SharePoint Development with Scrum

The session was spilt into two parts, an introduction to Scrum and a discussion about how this can be applied to SharePoint projects.  The audience was a good mix of Developers, Managers, ITPros, and business people with a range of exposure to Agile practices and Scrum.  The session provided everyone with an understanding of the terminology and process of doing Scrum.  There was a focus on ‘What is done’ and a good discussion around how you architect solutions.  For those that attended and anyone else interested I recommend you listen to Scott Hanselman’s podcast with Ken Schwaber where Ken covers these topics.  Also looking at the question ‘when do you architect solutions?’ I really like Kens take on how, using the waterfall approach, you have to spend time getting it right upfront. The ability to change later in the process is limited and the costs can be prohibitive.   Using agile techniques the architecture will emerge over time,  you know that you only have the architecture in place to support the business requirements developed.  He poses the question,  if you had defined the architecture up front what happens if it is changed mid way through the project?   With waterfall there is a lot of unpicking to be done and wasted effort.  With agile you don’t have to do the unpicking and the rigours of the process, ensuring things are done, means your code base is easier to change.

Being Agile with SharePoint

Here the focus was on facing the tough challenges early, understanding how to package your solutions, deployments to multiple environments, automation of processes and the eclectic mix of tasks you need to do to deal with the upgrade story.  There was a significant synergy with Ben Robb’s session on automated builds using Hyper-V and Robert Bogue’s coverage of the SharePoint Patterns and Practices coverage of upgrading.

I plan to do a screen cast of this session to provide some background to the slides and also the animations that really took me a long time to do.